Skip to content

WAF UPDATE: INSTALLATIONS WORKS AT NAGADO WATER TREATMENT PLANT WELL UNDERWAY

Installation works at the Nagado Water Treatment Plant is well underway on schedule as the Water Authority of Fiji (WAF) and its contractors work around the clock to restore water supply to its customers in Nadi and parts of Lautoka in the Western Division.

While inspecting the progress of works this morning, WAF Board Director, Kamal Gounder said that WAF was committed to complete the installation and repair works on time.

“Our teams are working around the clock to successfully complete this operation and we should complete the works by 10am tomorrow morning (30/09). We are expecting that water supply to low-lying areas be normalized by tomorrow evening and then the high elevated areas by Tuesday evening.

“In terms of the customers being affected, good news is that most of our customers living in Nadi Town, Denarau, and customers that are fed from the Black Rock Reservoir as they are getting water because we were able to commission the old main line that we used to operate before, this is providing level of water that we are able to supply to Denarau and some of the major customers in Nadi including the Airports Fiji Limited,” explained Mr Gounder.

Director Gounder said that WAF is only carting water for the other affected areas in Nadi as well as areas outside Lautoka City, and those not supplied through the Saru and Buabua Water Treatment Plants.

“I thank the residents of Nadi and Lautoka for taking head of our repeated warnings and alerts regarding the planned water shutdown. We are also thankful to the public for not vandalizing the many water tanks that we have placed around all affected areas, please continue to look after these tanks as this do not come cheap,” explained Mr Gounder.

WAF General Manager Customer Services, Mr Sekove Uluinayau said water carting trucks continue to service affected areas and refill the water tanks have been placed in strategic locations around Nadi and Lautoka tanks on a continual basis.

“A total of 58 water carting trucks have been deployed to refill the 206 water tanks (5300 and 10,000litre) that we had been placed at strategic locations around Nadi and Lautoka,” said Mr Uluinayau.

Mr Uluinayau said that after the installation works, water supply to customers residing in low-lying areas will be gradually restored and progressively to elevated areas once reservoir levels improve.

Meanwhile, customers in Nadi and Lautoka can contact the Authority through the emergency toll-free shortcode 1507 or email waterhelp@waf.com.fj for further enquiries which is available 24 hours a day.

Facebook
Twitter
LinkedIn
Email

What is the process and fee for a new water connection?

How much is the Lodgment fee?

  • House under construction / Vacant land / Commercial or Industrial
    • $101.00.
  • Completely built house. – [Please provide a letter from the lands department and/ or completion certificate ]
    • $21.95. [Please provide a letter from the lands department. completion certificate or Stamped Statutory declaration on the completion of the house]

Processing Time

  • Inspection to Approval – 15 Working days from the inspection date.
  • Installation – 30 Working days from payment of New Connection cost, on a first-come, first-serve basis. [Stakeholder processing may cause delays]. *Note: Approval of installation is valid for 3 months from the date of issue.

How much does the new connection cost?

  • Type A – $285 [“T” from existing connection] Type B $345 [direct connection from WAF main line]
  • New connection costs for Commercial and Industrial customers will be estimated according to requirements and a cost will be provided.
  • Road Crossing/ Service Enlargement is payable if required for additional meters requested. This will be communicated when the approval of internal and external stakeholders are obtained. WAF on behalf of FRA will refund any unused monies to the customer where applicable.