Replacement Works To Collapsed Wastewater Pipeline Along Kings Road Near 4 Miles Bridge Nears Completion.

The Water Authority of Fiji (WAF) would like to advise the public that replacement works to the collapsed wastewater pipeline at the 4 miles bridge along Kings Road is nearing completion.

The replacement works were challenging due to the conditions of the repair site and the teams have been working around the clock.

A large amount of time was spent to safely navigate between buried utility services which are laid above the wastewater trunk main.

Thankfully with the support and guidance of the teams from the Fiji Roads Authority(FRA), Telecom Fiji Limited and Energy Fiji Limited our team was able to safely replace the wastewater pipeline.

The repair site has been handed over to the FRA for backfilling and reinstating of the road.

We wish to thank our customers and the travelling public for their understanding and apologise for the traffic inconvenience caused as a result of these urgent repairs.

Motorists are advised that the Suva and Nausori bound lanes are still closed.

The FRA will make further announcements on the reopening of the road once their work is completed.

Traffic management is in place for those that require to go close to the cavity area only on official business and to residences off Kings Road.

Travellers along this area are advised to be mindful of the above when finalising travel plans.

Facebook
Twitter
LinkedIn
Email

What is the process and fee for a new water connection?

How much is the Lodgment fee?

  • House under construction / Vacant land / Commercial or Industrial
    • $101.00.
  • Completely built house. – [Please provide a letter from the lands department and/ or completion certificate ]
    • $21.95. [Please provide a letter from the lands department. completion certificate or Stamped Statutory declaration on the completion of the house]

Processing Time

  • Inspection to Approval – 15 Working days from the inspection date.
  • Installation – 30 Working days from payment of New Connection cost, on a first-come, first-serve basis. [Stakeholder processing may cause delays]. *Note: Approval of installation is valid for 3 months from the date of issue.

How much does the new connection cost?

  • Type A – $285 [“T” from existing connection] Type B $345 [direct connection from WAF main line]
  • New connection costs for Commercial and Industrial customers will be estimated according to requirements and a cost will be provided.
  • Road Crossing/ Service Enlargement is payable if required for additional meters requested. This will be communicated when the approval of internal and external stakeholders are obtained. WAF on behalf of FRA will refund any unused monies to the customer where applicable.