The Water Authority of Fiji (WAF) wishes to advise the public on the status of the Namulomulo Village Water Supply Scheme, with the timeline so far, to correct inaccuracies in an article titled โVillagers seek helpโ published on page 7 of the 8 November 2021 edition of Fiji Times.
Namulomulo Village, which is located outside the Water Authority of Fijiโs Urban Reticulated Water System, previously sourced its drinking water through rainwater harvesting systems, and water for cleaning through an existing borehole system.
WAF secured project funding of a total of $118,500 for Namulomulo Village within the 2017 โ 2018 Financial year for implementation of a new water scheme, which included the following:
– Construction of a new dam intake
– Construction of pump house and installation of a new pump
– Laying of rising main from pump to Village reticulation
– Reticulation of Namulomulo Village connecting to existing Rota Tanks
– Construction of 20 Standpipes and Showers
Works commenced in early 2018 with the mobilisation of team and materials to site to begin with the construction at the new dam intake site selected by the Village Water Committee of Namulomulo.
The damage of the dam was a result of heavy rain and flooding which scoured the river bank causing the collapse.
WAF then requested that the Village Water Committee identify an alternate site to be developed that would allow the project to be completed and closed out. While awaiting confirmation of the alternate site, our team continued working on the village reticulation and construction of the 20 standpipes and showers, which was then connected to the existing borehole system.
๐๐จ๐ซ๐๐ก๐จ๐ฅ๐ ๐๐ฒ๐ฌ๐ญ๐๐ฆ
In early 2019, WAF purchased a brand-new borehole pump out of its own budget to replace the existing old pump after it had developed mechanical issues, to get the water supply normalised to the village while awaiting the completion and replacement of the collapsed dam.
On 27 September, 2019, WAF received a report that the borehole pump had ceased operating, and on 3 October, 2019, a WAF team attended the site. Upon investigation, it was confirmed that the borehole pump failure had been caused by decomposed material within the suction end of the pump.
This was most likely a frog or rat that had got stuck in the borehole pump after entering from the open borehole casing and unmaintained borehole shelter, which was the responsibility of the Village Water Committee to maintain after handover. The pump was then transported to the WAF Pump workshop for cleaning, disinfection and servicing.
On 14 November, 2019, the WAF team on-site at Namulomulo flushed the borehole and removed debris build-up, including removal of decomposed material lodged inside the well, and on the following day, reinstalled the serviced and cleaned the borehole pump. Due to power issues at the time, testing of the pump was delayed until the electricity was back on.
The Turaga ni Koro and Village Water Committee were reminded again to make sure the open casing entry for pipe is well secured so no rats or frogs can enter the borehole pipe. They were further advised to restrict borehole pump operation hours to 6 hours per day to allow groundwater time to replenish and necessary downtime to minimise mechanical wear and tear of pumps as the pump was seen to be running dry.
On 26 November, 2019, after the Turaga ni koro advised that power issues were resolved, the Village Water Committee Chairman confirmed the testing of the pump and that the unit was operational. They were then advised of responsibility and duty of care as the asset was under their responsibility.
A week later, on 2 December, 2019, the WAF National Water Quality Laboratory testing confirmed the supply of water from the borehole was safe.
The following year, on 18 July, 2020, WAF was notified of a mechanical issue with the Namulomulo Borehole pump, which upon further investigation was revealed to be due to burn out of the pump motor, most likely due to the overrunning of the pump to the point where it was operating dry with no water in the borehole.
The Village Water Committee was advised to purchase a replacement pump as per their responsibility, which was agreed upon. So far, the new borehole pump has not been procured and installed on-site as agreed, which is why residents are currently experiencing issues with the water supply.
It is important to note that the management and operation of the borehole remains the responsibility of the Water Committee, as outlined in the Rural Water and Sanitation Policy of July 2021 below.
โSection 14.0 Policy Implementation โ Stakeholders Roles and Responsibilities; 14.9 Water Committee:
๐๐ข๐ต๐ฆ๐ณ ๐๐ฐ๐ฎ๐ฎ๐ช๐ต๐ต๐ฆ๐ฆ ๐ธ๐ช๐ญ๐ญ ๐ฉ๐ข๐ท๐ฆ ๐ต๐ฐ ๐ฆ๐ฏ๐ด๐ถ๐ณ๐ฆ ๐ต๐ฉ๐ฆ ๐ง๐ฐ๐ญ๐ญ๐ฐ๐ธ๐ช๐ฏ๐จ:
– ๐๐ข๐ฏ๐ข๐จ๐ฆ, ๐ฎ๐ข๐ช๐ฏ๐ต๐ข๐ช๐ฏ ๐ข๐ฏ๐ฅ ๐ฐ๐ฑ๐ฆ๐ณ๐ข๐ต๐ฆ ๐ธ๐ข๐ต๐ฆ๐ณ ๐ด๐ถ๐ฑ๐ฑ๐ญ๐บ ๐ข๐ฏ๐ฅ ๐ด๐ข๐ฏ๐ช๐ต๐ข๐ต๐ช๐ฐ๐ฏ ๐ด๐ค๐ฉ๐ฆ๐ฎ๐ฆ๐ด ๐ข๐ง๐ต๐ฆ๐ณ ๐ฉ๐ข๐ฏ๐ฅ๐ช๐ฏ๐จ ๐ฐ๐ท๐ฆ๐ณ;
– ๐๐ฏ๐ด๐ถ๐ณ๐ฆ ๐ธ๐ข๐ต๐ฆ๐ณ ๐ด๐ฐ๐ถ๐ณ๐ค๐ฆ๐ด ๐ข๐ฏ๐ฅ ๐ณ๐ฆ๐ด๐ฆ๐ณ๐ท๐ฐ๐ช๐ณ ๐ข๐ณ๐ฆ ๐ข๐ค๐ค๐ฆ๐ด๐ด๐ช๐ฃ๐ญ๐ฆ ๐ข๐ต ๐ข๐ญ๐ญ ๐ต๐ช๐ฎ๐ฆ๐ด;
– ๐๐ฆ๐ค๐ฐ๐ณ๐ฅ ๐ฏ๐ถ๐ฎ๐ฃ๐ฆ๐ณ ๐ฐ๐ง ๐ด๐ต๐ข๐ฏ๐ฅ ๐ฑ๐ช๐ฑ๐ฆ๐ด, ๐ฉ๐ฐ๐ถ๐ด๐ฆ๐ฉ๐ฐ๐ญ๐ฅ๐ด ๐ค๐ฐ๐ฏ๐ฏ๐ฆ๐ค๐ต ๐ต๐ฐ ๐ธ๐ข๐ต๐ฆ๐ณ, ๐ต๐บ๐ฑ๐ฆ ๐ฐ๐ง ๐ฃ๐ข๐ต๐ฉ๐ณ๐ฐ๐ฐ๐ฎ ๐ข๐ฏ๐ฅ ๐ต๐ฐ๐ช๐ญ๐ฆ๐ต๐ด ๐ข๐ฏ๐ฅ ๐ฆ๐ฏ๐ด๐ถ๐ณ๐ฆ ๐ต๐ฉ๐ข๐ต ๐ข๐ญ๐ญ ๐ญ๐ฆ๐ข๐ฌ๐ข๐จ๐ฆ๐ด ๐ข๐ณ๐ฆ ๐ณ๐ฆ๐ค๐ฐ๐ณ๐ฅ๐ฆ๐ฅ ๐ข๐ฏ๐ฅ ๐ณ๐ฆ๐ฑ๐ข๐ช๐ณ๐ฆ๐ฅ;
– ๐๐ฐ๐ญ๐ญ๐ฆ๐ค๐ต ๐ญ๐ฆ๐ท๐บ ๐ง๐ฐ๐ณ ๐ฑ๐ถ๐ณ๐ค๐ฉ๐ข๐ด๐ฆ ๐ฐ๐ง ๐ฑ๐ข๐ณ๐ต๐ด ๐ข๐ฏ๐ฅ ๐ต๐ฐ๐ฐ๐ญ๐ด ๐ง๐ฐ๐ณ ๐ต๐ฉ๐ฆ ๐ด๐ถ๐ด๐ต๐ข๐ช๐ฏ๐ข๐ฃ๐ญ๐ฆ ๐ฎ๐ข๐ฏ๐ข๐จ๐ฆ๐ฎ๐ฆ๐ฏ๐ต ๐ฐ๐ง ๐ต๐ฉ๐ฆ ๐ธ๐ข๐ต๐ฆ๐ณ ๐ด๐บ๐ด๐ต๐ฆ๐ฎ ๐ช๐ฏ ๐ต๐ฉ๐ฆ ๐ท๐ช๐ญ๐ญ๐ข๐จ๐ฆ ๐ข๐ฏ๐ฅ ๐ด๐ฆ๐ต๐ต๐ญ๐ฆ๐ฎ๐ฆ๐ฏ๐ต;
– ๐๐ฐ๐ณ๐ฌ ๐ธ๐ช๐ต๐ฉ ๐ต๐ฉ๐ฆ ๐๐ถ๐ณ๐ข๐จ๐ข ๐ฏ๐ช ๐ฌ๐ฐ๐ณ๐ฐ ๐ณ๐ฆ๐ค๐ฐ๐ณ๐ฅ๐ช๐ฏ๐จ ๐ฅ๐ข๐ฎ๐ข๐จ๐ฆ๐ด ๐ต๐ฐ ๐ธ๐ข๐ต๐ฆ๐ณ ๐ข๐ฏ๐ฅ ๐ด๐ข๐ฏ๐ช๐ต๐ข๐ต๐ช๐ฐ๐ฏ ๐ด๐บ๐ด๐ต๐ฆ๐ฎ ๐ฅ๐ถ๐ฆ ๐ต๐ฐ ๐ฅ๐ช๐ด๐ข๐ด๐ต๐ฆ๐ณ ๐ง๐ฐ๐ณ ๐ณ๐ฆ๐ฑ๐ฐ๐ณ๐ต๐ช๐ฏ๐จ ๐ฑ๐ถ๐ณ๐ฑ๐ฐ๐ด๐ฆ๐ด ๐ต๐ฐ ๐๐ข๐ต๐ฆ๐ณ ๐๐ถ๐ต๐ฉ๐ฐ๐ณ๐ช๐ต๐บ ๐ฐ๐ง ๐๐ช๐ซ๐ช, ๐ต๐ฉ๐ฆ ๐๐ฐ๐ฌ๐ฐ ๐๐ถ๐ช ๐ข๐ฏ๐ฅ ๐๐ช๐ด๐ต๐ณ๐ช๐ค๐ต ๐๐ง๐ง๐ช๐ค๐ฆ๐ณ๐ดโ ๐ฐ๐ง๐ง๐ช๐ค๐ฆ;
– ๐๐ฏ๐ด๐ถ๐ณ๐ฆ ๐ต๐ฉ๐ฆ ๐ค๐ญ๐ฆ๐ข๐ฏ๐ช๐ฏ๐จ ๐ฐ๐ง ๐ธ๐ข๐ต๐ฆ๐ณ ๐ด๐ฐ๐ถ๐ณ๐ค๐ฆ๐ด, ๐ฅ๐ข๐ฎ๐ด ๐ข๐ฏ๐ฅ ๐ณ๐ฆ๐ด๐ฆ๐ณ๐ท๐ฐ๐ช๐ณ๐ด ๐ฐ๐ฏ ๐ข ๐ฎ๐ฐ๐ฏ๐ต๐ฉ๐ญ๐บ ๐ฐ๐ณ ๐ฒ๐ถ๐ข๐ณ๐ต๐ฆ๐ณ๐ญ๐บ ๐ฃ๐ข๐ด๐ช๐ด ๐ข๐ฏ๐ฅ ๐ง๐ญ๐ถ๐ด๐ฉ๐ช๐ฏ๐จ ๐ฐ๐ง ๐ธ๐ข๐ต๐ฆ๐ณ ๐ฎ๐ข๐ช๐ฏ๐ด ๐ข๐ง๐ต๐ฆ๐ณ ๐ฉ๐ฆ๐ข๐ท๐บ ๐ณ๐ข๐ช๐ฏ๐ง๐ข๐ญ๐ญ; ๐ข๐ฏ๐ฅ
– ๐๐ฏ๐ด๐ถ๐ณ๐ฆ ๐ฑ๐ณ๐ฐ๐ฑ๐ฆ๐ณ ๐ฅ๐ณ๐ข๐ช๐ฏ๐ข๐จ๐ฆ ๐ด๐บ๐ด๐ต๐ฆ๐ฎ๐ด ๐ง๐ฐ๐ณ ๐ธ๐ข๐ด๐ต๐ฆ๐ธ๐ข๐ต๐ฆ๐ณ ๐ข๐ณ๐ฆ ๐ช๐ฏ ๐ฑ๐ญ๐ข๐ค๐ฆ ๐ข๐ฏ๐ฅ ๐ฑ๐ณ๐ฐ๐ฎ๐ฐ๐ต๐ฆ ๐ด๐ข๐ง๐ฆ ๐ข๐ฏ๐ฅ ๐ฉ๐บ๐จ๐ช๐ฆ๐ฏ๐ช๐ค ๐ฆ๐ฏ๐ท๐ช๐ณ๐ฐ๐ฏ๐ฎ๐ฆ๐ฏ๐ต ๐ช๐ฏ ๐ต๐ฉ๐ฆ ๐ท๐ช๐ญ๐ญ๐ข๐จ๐ฆ ๐ข๐ฏ๐ฅ ๐ด๐ฆ๐ต๐ต๐ญ๐ฆ๐ฎ๐ฆ๐ฏ๐ต.โ
Later in the year, WAF briefed and advised the Water Committee on the need to keep the borehole clean and well maintained following the flushing of the borehole that was carried out on 14 November, 2020. This was a concern, as similar advice had given previously, on 3 October 2019, when it had been initially noticed that there had been a lack of vigilance in carrying out duties.
Additionally, while undertaking the borehole flushing works, the teams removed debris lodged within the borehole casing, which seems to have been due to the shelter not being well maintained over time with no proper casing cover in place.
WAF staff were advised by the Village Headman of a suspected sabotage to their existing water infrastructure.
๐๐๐ฏ๐๐ฅ๐จ๐ฉ๐ฆ๐๐ง๐ญ ๐จ๐ ๐๐๐ฐ ๐๐๐ญ๐๐ซ ๐๐จ๐ฎ๐ซ๐๐
On 20 October, 2020, WAF received in writing confirmation from the Turaga ni Koro of Namulomulo Village of the intention to develop a new source on the Vatusoria Creek, and WAFโs rural surveyors inspected the new source.
It was determined that the scope of the works and cost required to develop the new source would be approximately $13,200, and the project was planned to be implemented as an in-house project.
Although site surveys were completed in March, 2021, our Rural Water Supply Team was unable to return to the site and Village Water Committee due to COVID-19 restrictions on movement, as a result of the 2nd wave of the pandemic, which also impacted the planning and procurement of the materials for this project.
๐ ๐ฎ๐ญ๐ฎ๐ซ๐ ๐๐ฅ๐๐ง๐ฌ
An update on the work done so far, work that will be carried out under this financial year, and assistance required to execute the improvement works has been provided to the Turaga ni Koro and Village Water Committee by WAF teams, along with representatives from Department of Water and Sewerage, who visited the village on 1 October, 2021.
A second visit will be conducted by the team today, 10 November, 2021 to provide the Turaga ni Koro and Water Committee with the implementation schedule for the development of the new source. Depending on the discussion during this visit, development is scheduled to begin as early as 22 November, 2021, provided the delivery of project materials remains unaffected and weather permitting.